Permit: TC-RES-0724-04094

Parcel: 119411550

Inspection Status: Re-inspection required

Inspection History: COT - RSBU - Interior Shear Bracing 

Date Description Inspector Results Comments
07/02/2025 COT - RSBU - Interior Shear Bracing  Re-inspection required Nails have penetrated more than an 1/8". Once corrections have been made they need to be taped and mud. Roof truss usually sits on interior wall so that the 5/8" type x is continuous from floor to ceiling. 7/2/2025
07/03/2025 COT - RSBU - Interior Shear Bracing  Re-inspection required Nails have penetrated more than an 1/8". Once corrections have been made they need to be taped and mud. Roof truss usually sits on interior wall so that the 5/8" type x is continuous from floor to ceiling. 7/2/2025

7/3/25: per previous notes. Not ready
07/07/2025 COT - RSBU - Interior Shear Bracing  Re-inspection required (with fee) 7-7-25: a/b required at 32" o.c. on exterior walls. Braced panel requires 4 a/b's per panel, add shot pins at marked locations, anchor bolts are required within 12" of a splice on each side, missing nails on exterior sheathing at /edges-joints throughout, loose roof panels-have framer walk entire roof and add nails accordingly.
07/08/2025 COT - RSBU - Interior Shear Bracing  Partial Pass 7-8-25: partial pass-firefoam all penetrations from interior side and reschedule inspection prior to installing drywall.
09/26/2025 COT - RSBU - Interior Shear Bracing  Not Applicable Duplicate inspection
09/26/2025 COT - RSBU - Interior Shear Bracing  Not Applicable Duplicate inspection