| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/04/2024 | COT - RSBU - Excavation/Rebar/Zoning | Not Ready | 1/4/23: not ready | |
| 01/17/2024 | COT - RSBU - Excavation/Rebar/Zoning | Not Ready | 1/4/24: not ready 1/17/24:not ready |
|
| 01/23/2024 | COT - RSBU - Excavation/Rebar/Zoning | Not Ready | 1/4/24: not ready 1/17/24:not ready 1/23/24: not ready |
|
| 01/24/2024 | COT - RSBU - Excavation/Rebar/Zoning | Re-inspection required | 1/4/24: not ready 1/17/24:not ready 1/23/24: not ready 1/24/24: footing at interior bearing wall requires width of 24" and is missing reinforcement, footing at perimeter of house missing reinforcement per plan. Plumbing in footing must be wrapped for protection from concrete. |
|
| 01/25/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 1/4/24: not ready 1/17/24:not ready 1/23/24: not ready 1/24/24: footing at interior bearing wall requires width of 24" and is missing reinforcement, footing at perimeter of house missing reinforcement per plan. Plumbing in footing must be wrapped for protection from concrete. 1/25/24: passed. |