Inspection Status: Partial Pass

Inspection History: BULD - Electrical Clearance

Date Description Inspector Results Comments
11/15/2023 BULD - Electrical Clearance Partial Pass Partial for the line-side tap, DGL Clearance was called into TEP at 1:15pm
11/28/2023 BULD - Electrical Clearance Passed Approved, DGC/DGL Clearance to TEP is required for the solar meter at unit #B