Inspection Status: Not Ready

Inspection History: COT - RSBU - Excavation/Rebar/Zoning 

Date Description Inspector Results Comments
09/25/2026 COT - RSBU - Excavation/Rebar/Zoning  Not Ready 9-25-26 not ready at this time. Will need to verify that plumbing was properly backfilled and compacted before moving on with this inspection.
09/29/2026 COT - RSBU - Excavation/Rebar/Zoning  Re-inspection required 9/29/26: footing depth not per plans, a 1 1/2" clearance from forms and DWV is required, tie off reinforcement at the north footing, compact pad and remove existing concrete at pad. An engineer RFI would be required if you chose to pour over existing concrete.
10/22/2026 COT - RSBU - Excavation/Rebar/Zoning  Passed 10/22/2026
Corrections made, verified engineer RFI document being uploading into TDC permit portal. Okay for concrete placement.