Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - RSBU - Excavation/Rebar/Zoning
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/25/2026 | COT - RSBU - Excavation/Rebar/Zoning | Not Ready | 9-25-26 not ready at this time. Will need to verify that plumbing was properly backfilled and compacted before moving on with this inspection. | |
| 09/29/2026 | COT - RSBU - Excavation/Rebar/Zoning | Re-inspection required | 9/29/26: footing depth not per plans, a 1 1/2" clearance from forms and DWV is required, tie off reinforcement at the north footing, compact pad and remove existing concrete at pad. An engineer RFI would be required if you chose to pour over existing concrete. | |
| 10/22/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 10/22/2026 Corrections made, verified engineer RFI document being uploading into TDC permit portal. Okay for concrete placement. |