Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
| Date |
Description |
Inspector |
Results |
Comments |
| 07/17/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Re-inspection required |
7-17-25: install hangers & anchor bolts per A3.1-2 detail's A1 & A2 for party wall at porch/party wall at storage. Anchor bolts are required at each end & side of party walls and shall be placed in the middle third of each sill plate. Either install hangers per plans or submit an RFI showing fix. |
| 07/24/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Re-inspection required |
7-24-25: not ready for inspection-waiting for RFI approval by the city. See previous notes from inspection on 7-17-25 regarding detail in question together with anchor bolt requirements at storage and porch party wall. |
| 07/28/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Not Ready |
|
| 09/03/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Passed |
|