Inspection Status: Partial Pass

Inspection History: RSBU - Building Final 

Date Description Inspector Results Comments
09/29/2026 RSBU - Building Final  Partial Pass 9/28/2026 Partial pass. Ensure sub panel is bonded/grounded. Replace breakers with afci breakers. Provide WR receptacles at all outdoor locations. Label j box. Provide full cut off lights at outdoor area. Replace mirage mini split due to not being UL listed. Ensure there is a 3" clearance from grade at unit. Secure new unit to pad. Provide disconnect near and off to the side of unit. Secure seal tight 12" from disconnect.
11/04/2026 RSBU - Building Final  Passed 11/04/2026
All corrections made.