Inspection History Details
Inspection Status: Not Ready
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/03/2026 | BULD - Electrical Clearance | Not Ready | 03/03/2026 No response from field contact. |
|
| 03/17/2026 | BULD - Electrical Clearance | Re-inspection required | never heard from contractor | |
| 04/07/2026 | BULD - Electrical Clearance | Not Ready | Per previous notes. 4/7/2026 | |
| 04/21/2026 | BULD - Electrical Clearance | Not Ready | ||
| 04/30/2026 | BULD - Electrical Clearance | Partial Pass | 4.30.26 Approved for incr clearance, cutover |
|
| 05/19/2026 | BULD - Electrical Clearance | Canceled | ||
| 06/09/2026 | BULD - Electrical Clearance | Canceled | 06/09/2026 Canceled at contractor request. |
|
| 06/23/2026 | BULD - Electrical Clearance | Passed | 6/23/2026 clearance for TEP DGC. |