Inspection Status: Re-inspection required
Inspection History: BULD - Electrical Clearance
| Date |
Description |
Inspector |
Results |
Comments |
| 12/02/2025 |
BULD - Electrical Clearance |
|
Re-inspection required |
Called, Field contact name : Mario Sanchez, phone number: (520) 481-3332. Conflicting information about work done at this residence; Permit was pulled by Ace heating and cooling; however, customer states that they have never heard of Ace heating and cooling, but Prime Mechanical replaced swamp cooler in April 2025 but was told that MSP would need to be upgraded in order to install new A.C. Unit. Furthermore, work has been complete without permit and contractor did not submit an application with TEP for panel upgrade. |