Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - RSBU - Excavation/Rebar/Zoning
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/08/2025 | COT - RSBU - Excavation/Rebar/Zoning | Partial Pass | 8.8.2025 Partial pass pending final post. |
|
| 08/29/2025 | COT - RSBU - Excavation/Rebar/Zoning | Partial Pass | 8-29-25: RFI submitted to the city for vertical reinforcement spacing at stem wall to 24" o.c. at stem. Verified installation of missing post, grounding rods/ and grounding at reinforcement -Okay to pour at own risk. | |
| 09/25/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 9-25-25: slab on grade verified per revision -okay for concrete placement at progress areas. |