Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Partial Pass

Inspection History: COT - RSPL - Rough Soil 

Date Description Inspector Results Comments
COT - RSPL - Rough Soil  Partial Pass 9/28/23: sewer connections on opposite side of house plans must be revised. All plumbing under pressure.
09/28/2023 COT - RSPL - Rough Soil  Partial Pass 9/28/23: sewer connections on opposite side of house plans must be revised. All plumbing under pressure.
10/17/2023 COT - RSPL - Rough Soil  Partial Pass 10/17/23 under slab OK to proceed concrete is doweled and pre-slab complete, site sewer still needs to be accomplished to HCS or septic
10/17/2023 COT - RSPL - Rough Soil  Passed
12/05/2023 COT - RSPL - Rough Soil  Passed