Inspection Status: Partial Pass
Inspection History: COT - RSPL - Rough Soil
| Date |
Description |
Inspector |
Results |
Comments |
|
COT - RSPL - Rough Soil |
|
Partial Pass |
9/28/23: sewer connections on opposite side of house plans must be revised. All plumbing under pressure. |
| 09/28/2023 |
COT - RSPL - Rough Soil |
|
Partial Pass |
9/28/23: sewer connections on opposite side of house plans must be revised. All plumbing under pressure. |
| 10/17/2023 |
COT - RSPL - Rough Soil |
|
Partial Pass |
10/17/23 under slab OK to proceed concrete is doweled and pre-slab complete, site sewer still needs to be accomplished to HCS or septic |
| 10/17/2023 |
COT - RSPL - Rough Soil |
|
Passed |
|
| 12/05/2023 |
COT - RSPL - Rough Soil |
|
Passed |
|