Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Re-inspection required

Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.

Date Description Inspector Results Comments
06/03/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required Please install heating and cooling mini split as per plan and Hilow combustion air relief for water heater
6/3/25: Receptacle spacing not per plan, combustion air for water heater not per plan, window sill height not code complaint, Exterior receptacles over by mini splits must be WR GFCI and must have approved cover, insulation at refrigerant lines must be wrapped and protected from UV, Disconnect boxes must be properly secured and cover plates must be installed at time of inspection, fuses were not verified due to cover plates missing and loose connections, please label disconnect boxes, mini splits must be 3" above grade, condensation missing at east unit. Exterior Plastic piping must be coated for UV protection, label breakers to correspond with new rooms, construction was completed and covered prior to inspections being called in. We will have to verify framing, electrical, and all new construction prior to issuance of CofO.
11/07/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed