Inspection History Details
Inspection Status: Not Ready
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/18/2024 | BULD - Electrical Clearance | Not Ready | NR, missing grounding and bonding | |
| 09/27/2024 | BULD - Electrical Clearance | Partial Pass | Partial for the 200A service panel upgrade - INCR Clearance to TEP is required for the cutover Pending solar meter |
|
| 10/28/2024 | BULD - Electrical Clearance | Partial Pass | Verified TEP field tech riser height and address label - Partial for the 200A service panel upgrade - (resend) INCR Clearance to TEP is required for the cutover Pending solar meter |
|
| 11/21/2024 | BULD - Electrical Clearance | Passed | Approved - DGC Clearance to TEP is required for the solar meter |