Inspection Status: Partial Pass
Inspection History: COT - RSBU - Exterior/Interior Clips/Sheathing/Framing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/25/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Partial Pass | 11/15/23: 1-hour fire wall at storage not per plan requires 5/8 type x on exterior side, weep screed clearance will not be met at final on eats and south of storage. 11/21/23: corrections made at 1-hour firewall on east exterior wall at storage room. Ok to proceed at storage. 1/25/24: roof nailing in great room alteration and bedroom 4 passed. ok to dry-in. sheathing on exterior passed. Revision will need to be made on 2x12 hangers on detail S3/10. Post caps not installed at 6x6 post supporting GLM beam, opening for exterior door missing trimmer studs. |
|
| 04/24/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 11/16/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Re-inspection required | 11/15/23: 1-hour fire wall at storage not per plan requires 5/8 type x on exterior side, weep screed clearance will not be met at final on eats and south of storage. | |
| 11/21/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Partial Pass | 11/15/23: 1-hour fire wall at storage not per plan requires 5/8 type x on exterior side, weep screed clearance will not be met at final on eats and south of storage. 11/21/23: corrections made at 1-hour firewall on east exterior wall at storage room. Ok to proceed at storage. |