Inspection History Details
Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/26/2025 | BULD - Electrical Clearance | Partial Pass | Partial for the Enphase meter switch - DGL Clearance was called into TEP at 10:05 am Pending solar |
|
| 07/02/2025 | BULD - Electrical Clearance | Passed | 7.2.25 Solar installed per plans |