Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - BULD - SWG Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/19/2024 | COT - BULD - SWG Clearance | Partial Pass | Previous page of results should be changed to the following. Clearance to SWG has been retracted. Gas clearance should not be given until finals are approved, due to the unknown complexity of gas piping yet to be done. A new pressure test should be done at finals. 30 ‘ underground run ok to backfill. |
|
| 04/11/2024 | COT - BULD - SWG Clearance | Re-inspection required | No response 4/11/24 | |
| 04/18/2024 | COT - BULD - SWG Clearance | Not Ready | 4/18/24 - need remaining distribution gas piping pressure tested and ready to attach to the mechanical components, for final. | |
| 05/03/2024 | COT - BULD - SWG Clearance | Passed |