Inspection History Details
Inspection Status: Passed
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
Permit Number - TC-RES-0223-03082
Inspection Description - COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/06/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
09/15/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Not Ready | 1-Trap arm length for guest lavatory is more than 6'. 2-T and P line is in PVC. 3-DWV piping is leaking. Stopped inspection. | |
09/27/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Re-inspection required | Provide DWV test. Master bedroom calls for double vanity. Receptacle needs to be moved over near stove, within 2' of stove. Add nail plates to any plumbing and electrical that is within an 1" 1/4. RFI on hallway going to the back door. Plans are not calling for that detail. Revise plans or provide option. Fire foam top penetrations and seal off any electrical boxes with day light coming through. 9/27/2023 | |
09/29/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Re-inspection required | 9/29/23: missing straps mid story on plumbing, revision needed on hallway and egress door that is not on plans, master bath missing double vanity | |
11/06/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Re-inspection required | 11/6/23: missing double vanity at master bedroom | |
11/06/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Re-inspection required | 11/6/23: missing double vanity at master bedroom | |
11/09/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed |