| 01/28/2025 |
COT - RSME - Mechanical Final |
|
Partial Pass |
1-28-25, partial pass for split unit. Condenser installation on top of roof was verified per code. However, furnace/air handler installation was not complete so contractor will reschedule that portion when ready. |
| 01/29/2025 |
COT - RSME - Mechanical Final |
|
Canceled |
1/29/25: Cancelled by contractor. Not ready furnace/air handler installation not completed. |
| 06/26/2025 |
COT - RSME - Mechanical Final |
|
Passed |
6/26/25 furnace installed per code |