Inspection Status: Re-inspection required
Inspection History: COT - RSPL - Rough Soil
| Date |
Description |
Inspector |
Results |
Comments |
| 04/16/2025 |
COT - RSPL - Rough Soil |
|
Re-inspection required |
4/16/25: plumbing underground not per approved plans, not under test (air must be released from plumbing pipes and filled with water), tracer wire required. NOT READY. RE-INSPECTION REQUIRED. |
| 04/17/2025 |
COT - RSPL - Rough Soil |
|
Re-inspection required |
4-17-25, no answer on pre all or at the residence. |
| 04/25/2025 |
COT - RSPL - Rough Soil |
|
Re-inspection required |
4/25/2025 plumbing not under test. Plans not on site. Remove all rocks from plumbing lines. |
| 04/29/2025 |
COT - RSPL - Rough Soil |
|
Re-inspection required |
4-29-25, plumbing underground not per approved plans. Remove all rocks from trench and sleeve/wrap copper water line and plumbing at footings. |
| 05/02/2025 |
COT - RSPL - Rough Soil |
|
Passed |
5-2-25, plumbing underground verified under test and per plans. Okay to backfill with shading material. |