Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
| Date |
Description |
Inspector |
Results |
Comments |
| 04/30/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Re-inspection required |
Provide DWV test. Remove wall from sub panel. Fire foam all top penetrations. Seal all exterior penetrations. Expose sewer, water and electrical lines. Remove hardy board from shower prior to inspection. 4/30/2025 |
| 05/08/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Partial Pass |
Partial pass. Sewer line and water lines exposed along with tracer wire in place for both lines. They're in the same trench but have a minimum of 12" separation. Okay to backfill at. Shading required. 5/8/2025 |
| 05/13/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Not Ready |
|
| 05/14/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Passed |
Ok to insulate and cover walls. |