Inspection Status: Re-inspection required

Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.

Date Description Inspector Results Comments
04/20/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required 4-20-23: 1-Expose water piping that was re-piped. 2-Install smoke detectors per approved plans. 3-Front bedroom windows do not meet requirements of R310.2.1. 4-Services are not per approved plans. 5-Overhead conductors do not meet the minimum requirements of E3604.2.1. 6- Install lights at carport per approved plans. 7- Provide engineering for attachment of New wood fascia and rafters to existing house, or provide permit number to verify compliant installation of as-built condition.
Note: If carport was installed at time of Stop Work Order, it is not considered existing.
07/17/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required
08/30/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required (with fee) 1-Service is still not per plans. 2-b-vent needs 1” clearance to combustibles. 3-Obtain separate permit for unit 2.
09/14/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required 4-20-23: 1-Expose water piping that was re-piped. 2-Install smoke detectors per approved plans. 3-Front bedroom windows do not meet requirements of R310.2.1. 4-Services are not per approved plans. 5-Overhead conductors do not meet the minimum requirements of E3604.2.1. 6- Install lights at carport per approved plans. 7- Provide engineering for attachment of New wood fascia and rafters to existing house, or provide permit number to verify compliant installation of as-built condition.
Note: If carport was installed at time of Stop Work Order, it is not considered existing.

Sink trap arm is too high.
Connect Ufer and ground rods to both services.
Install b vent for water heater.
Install CO detector.

Note: Corrections for unit 2:
Remove drywall at laundry and kitchen sink to depose water piping.
Expose one switch and one receptacle in each room.
Provide gas test.
Provide approved building plans.
Expose b vent.
Door to bedroom swings over step.
Panel can not be in clothes closet.
Kitchen receptacles can not be over stove.
Counter to right of stove needs receptacle.
Separate ground from neutral at sub panel.
Smoke detectors and CO detectors not installed.
Combustion air can not be from inside habitable space.
Provide ladder for roof inspection.
Bedroom doors can not have locks if sub panel is in bedroom.
Ground rods are less than six feet apart.
Expose b vent for water heater

9/14/23: revise plans/permit to show inspections for unit 1 on the correct permit and inspections for unit 2 on the correct permit.
09/20/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass Partial approval for water piping, emergency egress, B vent clearance, electrical receptacle wiring corrections were addressed. Pending revised plan approval, to address the pending electric services,carport construction, separation of units 1 and 2 comments. Revisions must be approved and on site prior to Final inspection
10/25/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed