Inspection Status: Re-inspection required
Inspection History: RSBU - Building Final
| Date |
Description |
Inspector |
Results |
Comments |
| 04/07/2023 |
RSBU - Building Final |
|
Re-inspection required |
April 7th: Met owner rep Frank at the site to discuss what areas of wallboard are to opened up for inspection next week. I requested ladders to access attic and the roof. Manufactures installation specs for fireplace, remove two outlets in each room( do not unland the wires) provide permit for new panel board, remove all flexible pipe under bathroom lavatory's |
| 04/13/2023 |
RSBU - Building Final |
|
Re-inspection required |
Romex wire appears to be unattached to the framing within 12" of the electric boxes. Open all walls 18" above all wall outlets and switches for field inspection. They new PEX and ABS appear to be compliant, however it also was installed without permit and inspection. The new roof package unit and interior air handler appear compliant and fused per manufacture's specs. |
| 04/26/2023 |
RSBU - Building Final |
|
Passed |
|