Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - RSBU - Roof Nailing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/09/2025 | COT - RSBU - Roof Nailing | Not Ready | Entire wall and door near staircase disconnected | |
| 05/12/2025 | COT - RSBU - Roof Nailing | Re-inspection required | Entire wall and door near staircase disconnected Entire wall and door near staircase disconnected 5/12/25 1. Stairs not per plan, requires A34 clips at each stringer, requires 2x8 blocking at the top of the stairs. 2. LTP4's required in garage north and south shear walls. See detail 208. 3. Attic access compromised, hvac drain pan is encroaching into access. 4. Upstairs East bedroom, truss blocking is loose and needs to be nailed down. |
|
| 05/16/2025 | COT - RSBU - Roof Nailing | Passed | 5/16/25 corrections made |