Inspection Status: Not Ready

Inspection History: RSBU - Building Progress

Permit Number - TC-MDP-1123-01829

Inspection Description - RSBU - Building Progress

Inspection Status - Not Ready

Date Description Inspector Results Comments
04/03/2024 RSBU - Building Progress Not Ready obtain partial approval of Electric final for use as Model home.
04/26/2024 RSBU - Building Progress Partial Pass Mechanical and electrical fixtures are installed and being powered by a portable generator that is properly grounded and connected directly into the electrical panel. Water is connected to the meter, but not turned on because sewer connection has not been approved by the county. A porta-John and hand washing station are provided outside the building in the parking area. Okay to issue a Level 4 Temporary Certificate of Occupancy for K B Homes to use building as a Construction Office/Model Home.
08/25/2024 RSBU - Building Progress Passed 8/23/24: Construction is complete. Electrical, water, and sewer connections have been completed. All mechanical, electrical, and plumbing fixtures are installed and fully operational. Electrical panel is properly labeled with AFCI/GFCI breakers installed as required. K B Homes will be utilizing this as their Model Home until entire subdivision is completed. Okay to issue Permanent Certificate of Occupancy.