Inspection Status: Not Ready
Inspection History: RSBU - Building Progress
Permit Number - TC-MDP-1123-01829
Inspection Description - RSBU - Building Progress
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/03/2024 | RSBU - Building Progress | Not Ready | obtain partial approval of Electric final for use as Model home. | |
04/26/2024 | RSBU - Building Progress | Partial Pass | Mechanical and electrical fixtures are installed and being powered by a portable generator that is properly grounded and connected directly into the electrical panel. Water is connected to the meter, but not turned on because sewer connection has not been approved by the county. A porta-John and hand washing station are provided outside the building in the parking area. Okay to issue a Level 4 Temporary Certificate of Occupancy for K B Homes to use building as a Construction Office/Model Home. | |
08/25/2024 | RSBU - Building Progress | Passed | 8/23/24: Construction is complete. Electrical, water, and sewer connections have been completed. All mechanical, electrical, and plumbing fixtures are installed and fully operational. Electrical panel is properly labeled with AFCI/GFCI breakers installed as required. K B Homes will be utilizing this as their Model Home until entire subdivision is completed. Okay to issue Permanent Certificate of Occupancy. |