Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 06/20/2025 |
ENGR Engineering Final
|
|
Not Ready |
Drain block needs to be installed in wall. |
| 06/23/2025 |
ENGR Engineering Final
|
|
Not Ready |
Not Ready without Sewer Back water valves in each unit or a signed letter from Surveyor/Engineer stating they are not needed. Expose the sidewalk scuppers in front so they don’t get clogged with debris as fast and function better. Ensure grade in back yard is such that water drains out of drain block in wall and does not puddle. |
| 06/25/2025 |
ENGR Engineering Final
|
|
Partial Pass |
Okay for level 4 TCO. Pending resolution of Sewer Backwater valve needed for C of O. |
| 08/27/2025 |
ENGR Engineering Final
|
|
Passed |
Replace the dg that is missing in small area next to replaced sidewalk panel in front of front door. |