Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
Permit Number - TC-MDP-1024-01201
Inspection Description - COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
Inspection Status - Re-inspection required
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/24/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Re-inspection required | 4-24-25, minimum of 2 screws required for metal bracket that holds pex lines at bathroom, secondary HVAC pvc not extended to the exterior, a 12" clearance is required between pex lines & can lights- relocate pex to allow clearance requirements or block with 2x4, osb, plywood or drywall.add bank plates where electrical wires are within 1 1/4" from edge of studs- required near 4-gang box near back sliding glass door | |
| 04/28/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Re-inspection required | 4/28/25: seal penetration through vapor barrier at bedroom north west, secure nm cable near attic access, FHA PLATE behind kitchen exhaust, seal top plate penetration at bathroom. | |
| 04/30/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 4-24-25, minimum of 2 screws required for metal bracket that holds pex lines at bathroom, secondary HVAC pvc not extended to the exterior, a 12" clearance is required between pex lines & can lights- relocate pex to allow clearance requirements or block with 2x4, osb, plywood or drywall.add bank plates where electrical wires are within 1 1/4" from edge of studs- required near 4-gang box near back sliding glass door. 4/28/25: seal penetration through vapor barrier at bedroom north west, secure nm cable near attic access, FHA PLATE behind kitchen exhaust, seal top plate penetration at bathroom. 4/30/25: CORRECTIONS MADE OK TO PROCEED |