Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/31/2025 | ENGR Engineering Final | Not Ready | 1) ensure all drainage is flowing away from the foundation to lot drainage. 2) low grade at electrical panel 3) blocked side to side drainage at several locations. 4) island missing light pole and tree. 5) drainage area at northwest side of building is showing signs of holding water. 6) East side of building where water will run from building 10 to 8 does not look like it will get around the corner. 7) re-stake all trees correctly |
|
| 08/01/2025 | ENGR Engineering Final | Deferred |