Inspection Status: Canceled

Inspection History: COT - BULD - SWG Clearance

Date Description Inspector Results Comments
03/28/2024 COT - BULD - SWG Clearance Canceled 3/28/24: canceled per contractor
04/02/2024 COT - BULD - SWG Clearance Re-inspection required Pex line connections to copper line must be min. 18” away from next soldered joint per M2105.10.2, duct registers must be blocked on 3 sides.
3/28/24: canceled per contractor
4/2/24: pex line connection to copper still not at min 18" of copper.
05/30/2024 COT - BULD - SWG Clearance Passed