Inspection Status: Re-inspection required

Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.

Date Description Inspector Results Comments
04/14/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required 4/14/25
1. 14/2 romex in garage not terminated, hanging from top plate.
2. All penetrations in top plate in garage is open.
3. Top plate penetrations open in every room.
4. Nail plates required throughout
5. Boca plates required throughout
****STOPPED INSPECTION*** not ready, more items may be added on re-inspection.
04/16/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required 4/16/25
1. UFER not connected.
2. Bang plates needed throughout, marked with red X on studs.
04/18/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required 18 April 25
No corrections made.
04/22/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 4-22-25, intermediates approved. Okay to continue with construction.