Inspection Status: Passed

Inspection History: COT - RSBU - Excavation/Rebar/ZoningĀ 

Date Description Inspector Results Comments
01/29/2025 COT - RSBU - Excavation/Rebar/ZoningĀ  Passed Concrete forms are set, post tension cabling is properly installed per plans, additional rebar is installed per plans, shear wall braces are installed, masa clips are installed 32" on center, Ufer ground is installed, underground plumbing is properly wrapped with foam, underground electrical is installed for kitchen island. Okay to proceed with concrete pour.