Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: COT - RSBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 01/29/2025 |
COT - RSBU - Preslab |
|
Passed |
Concrete forms are set, post tension cabling is properly installed per plans, additional rebar is installed per plans, shear wall braces are installed, masa clips are installed 32" on center, Ufer ground is installed, underground plumbing is properly wrapped with foam, underground electrical is installed for kitchen island. Okay to proceed with concrete pour. |