Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Re-inspection required
Inspection History: RSBU - Building Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/01/2024 |
RSBU - Building Final |
|
Re-inspection required |
10/1/24: t and p line needs to be terminated 6 inches from final grade. 1 of the Kitchen circuits does not have power. Missing labeling inside main panel. Main panel is not wired to reflect electrical plan. |
| 10/17/2024 |
RSBU - Building Final |
|
Re-inspection required |
10-17-24, missing door bell, thermostat heights in kitchen and two bedrooms not installed per approved plans, missing arch fault circuit in laundry, main water line under repaired-requires verification of proper operation, missing bonding at gas line. |
| 10/23/2024 |
RSBU - Building Final |
|
Passed |
10/21/24: Button switch for door bell has been installed, thermostats have been lowered to 54", arch fault breaker installed for laundry room, main water line has been repaired and under street pressure, gas bond grounding wire has been installed. Al construction work is complete. Okay to issue Certificate of Occupancy. |