Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: COT - RSBU - Excavation/Rebar/ZoningĀ
| Date |
Description |
Inspector |
Results |
Comments |
| 08/23/2024 |
COT - RSBU - Excavation/Rebar/ZoningĀ |
|
Passed |
Concrete forms are set, post tension cabling is properly spaced per pan, masa clips are attached to form at a 2' spacing, shear wall clips are attached to form per plan, rebar reinforcement is installed as required by plan, Ufer ground is installed on transformer side of garage, and all underground plumbing is properly wrapped with foam. |