Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: RSBU - Building Progress
Permit Number - TC-MDP-0823-01314
Inspection Description - RSBU - Building Progress
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/01/2024 | RSBU - Building Progress | Passed | Construction, mechanical, plumbing, and electrical are complete. Mechanical, plumbing, and electrical fixtures are installed and operational. AFCI breakers are installed in electrical panel for all circuits. GFCI outlets are installed in kitchen, laundry, bathrooms, and garage. Okay to issue Certificate of Occupancy once all other departments have signed off permit. |