Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - RSPL - Rough Soil
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/16/2026 | COT - RSPL - Rough Soil | Re-inspection required | 1. No plans on site, plans provided via email calls for 4" sewer line, also missing gray water piping. | |
| 10/20/2026 | COT - RSPL - Rough Soil | Not Ready | ||
| 10/26/2026 | COT - RSPL - Rough Soil | Not Ready | ||
| 11/17/2026 | COT - RSPL - Rough Soil | Re-inspection required | 1-Provide approved plans. 2-New sewer line has multiple leaks. 3-All fittings and joints need to be exposed 360 degrees for inspection. 4- There is no gray water piping. 5-Digital plans do not have setbacks noted. |
|
| 11/19/2026 | COT - RSPL - Rough Soil | Partial Pass |