Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
| Date |
Description |
Inspector |
Results |
Comments |
| 01/03/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Re-inspection required |
1-3-24, panel schedule not per approved plans-provide an updated schematic to the city for review and approval. Fire foam all penetrations at top plates. Pex in several locations is w/in 12 inches of a can lights. Provide blocking or insulation at affected areas. |
| 01/06/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Re-inspection required |
1-6-25, no plans on site. See previous notes with regards to missing firefoam. |
| 01/07/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Partial Pass |
1-7-25, okay to proceed construction at own risk. Waiting on updated electrical schematic for panel schedule. Additionally, this model will be temporarily used as a sales office and the garage has been constructed to fit those needs. Contractor has submitted a revision to the city for review and will be obtaining an additional permit. Meanwhile, permission has been granted to continue construction but will be done at own risk. |
| 02/13/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Partial Pass |
2/13/25 main panel missing breakers. |
| 12/23/2024 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Not Ready |
12/23/24 Water not under pressure, vapor barriers must be sealed a penetrations and stud shoes are required where mini splits penetrate. |