Inspection History Details
Inspection Status: Re-inspection required
Inspection History: ENGR Engineering Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/13/2026 | ENGR Engineering Final | Re-inspection required | Site does not have positive drainage away from building foundation. West side has pooling next to the slab. | |
| 07/14/2026 | ENGR Engineering Final | Not Ready | Conditions on the permit need to be satisfied prior to final. The unsatisfied conditions are: -Air Leakage and Duct Tightness -Sewer Release -Zoning Hold When these documents have been submitted and the conditions have been satisfied in the portal, the engineering final can pass. |
|
| 07/20/2026 | ENGR Engineering Final | Not Ready | Outstanding conditions are still not satisfied prior to final: -Air leakage and duct tightness, -Sewer Release Submit required Documents and allow intake to satisfy for final. |
|
| 07/21/2026 | ENGR Engineering Final | Passed |