Inspection Status: Passed
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
| Date |
Description |
Inspector |
Results |
Comments |
| 01/08/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Passed |
1/8/25 variance granted by TEP |
| 12/16/2024 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Re-inspection required |
12-16-24, missing fire foam at condensation line, seal all penetrations, nail all h-25's at interior load bearing walls, block register at laundry room, and fix tear to duct in teen room. The window adjacent to the electrical panel is within 3 feet. Per code, a 3 foot clearance is required around panel. |
| 12/17/2024 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Partial Pass |
12/17/24 partial pass pending relocation of main service panel. Ok to proceed inside at own risk. |