Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
| Date |
Description |
Inspector |
Results |
Comments |
| 11/26/2024 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Re-inspection required |
11-26-24, missing fire foam at bedroom 4, secure mechanical line set with strap in family room, seal vapor barrier at upstairs primary bathroom, also vent in same bathroom not connected, shower not under test. Electrical schedule does not match with what actually exists. Have electrical company submit a letter and an updated schematic. Submit to the city for review. Stopped inspection, additional items may be added |
| 11/29/2024 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Re-inspection required |
11-29-24, seal vapor barrier at marked locations throughout bottom floor. |
| 12/05/2024 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Passed |
12-5-24, residential intermediate inspection approved. Okay to continue with construction. |