Inspection Status: Partial Pass

Inspection History: COT - LCBU - Framing

Date Description Inspector Results Comments
02/14/2024 COT - LCBU - Framing Partial Pass 2/14/24: framing inspection passed first floor . Pending Anchor bolt fix throughout at shear walls on foundation.
02/15/2024 COT - LCBU - Framing Partial Pass 1/16/24: holdowns at first floor per plan ok to proceed. Shear walls at first floor per plan ok to proceed.
1/31/24: holdowns at second floor per plan ok to proceed. Shear walls at second floor per plan ok to proceed.
2/15/24: framing at building 4 passed. detail approves shot pins at 18” O.C at 2 story building at interior shear walls.
06/07/2024 COT - LCBU - Framing Passed 2/14/24: framing inspection passed first floor . Pending Anchor bolt fix throughout at shear walls on foundation.
1/16/24: holdowns at first floor per plan ok to proceed. Shear walls at first floor per plan ok to proceed.
1/31/24: holdowns at second floor per plan ok to proceed. Shear walls at second floor per plan ok to proceed.
2/15/24: framing at building 4 passed.
6/7/24: framing at second floor passed.