Inspection Status: Re-inspection required

Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.

Permit Number - TC-MDP-0523-00999

Inspection Description - COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
11/28/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required Uffer installed incorrectly, garage lights not per plans according to E1. Incorrect wire sizes. Garage lights also connecting to hallway and den. Not per plans, seal penetration at vapor barrier right side of garage, pex lines within 12” of can lights must be insulated, water lines not connected/completed, DWV not under test, showers/tubs not under test, secure copper line in master bathroom shower, incorrect wire sizes for outside receptacles. Not per E1 plan. Stopped inspection. Check house for code compliance before calling for inspection.
12/01/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required Not ready. Check house for code compliance before calling for inspection.
12/04/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass 12-4-23: Mechanical and plumbing are complete. Still need plan revision for garage lighting circuit and install 12 gauge wire for all exterior outlets, including the equipment service outlet.
12/11/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed