Inspection Status: Re-inspection required
Inspection History: COT - RSPL - Rough Soil
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/07/2025 | COT - RSPL - Rough Soil | Re-inspection required | 07 April 25 1. No underground plumbing plan. 2. Tracer on water line needs to be blue and at least a number 14AWG. |
|
| 04/10/2025 | COT - RSPL - Rough Soil | Partial Pass | 07 April 25 1. No underground plumbing plan. 2. Tracer on water line needs to be blue and at least a number 14AWG. 4/10/25: main water line per plan. Corrections made ok to proceed with backfill. Shading required, Plumbing underground not per plan, laundry room was missed on plans and will get the revised set approved and submitted.intermediate inspections will not be completed until revised set had been approved |
|
| 08/08/2025 | COT - RSPL - Rough Soil | Passed |