Inspection Status: Re-inspection required
Inspection History: RSBU - Building Final
| Date |
Description |
Inspector |
Results |
Comments |
| 12/14/2023 |
RSBU - Building Final |
|
Re-inspection required |
12/14/23:toilets not caulked on first floor. A/C unit not wired. missing post tension tag at hose bib. exhaust fan in laundry not installed. t and p line needs to be cut 6 inches from earth. communications lines in laundry needs to be secured to wall. |
| 12/15/2023 |
RSBU - Building Final |
|
Passed |
12/15/23: Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled. GFCI outlets are installed where required. Outdoor lights are installed per plan and operational. Okay to issue Certificate of Occupancy when all other agencies have completed their final inspections. |