Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
Permit Number - TC-MDP-0324-00297
Inspection Description - COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
Inspection Status - Re-inspection required
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Re-inspection required | 10/3/24: Thermostat shall be no higher than 54" above finish grade, strap required at living room GLB, pex requires 12" clearance from can light, kitchen hood duct must be properly installed in wall, block registers on three sides at entrance, secure NM cable. 12" from fixture, seal penetrations at vapor barrier. | ||
10/07/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Re-inspection required | Leak at 3" ABS line in downstairs bathroom. Re secure cs16 strap in closet at entry. 10/72024 | |
10/08/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Re-inspection required | Per previous notes. Leak at 3" ABS line. 10/8/2024 | |
10/10/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Re-inspection required | 10/3/24: Thermostat shall be no higher than 54" above finish grade, strap required at living room GLB, pex requires 12" clearance from can light, kitchen hood duct must be properly installed in wall, block registers on three sides at entrance, secure NM cable. 12" from fixture, seal penetrations at vapor barrier. Leak at 3" ABS line in downstairs bathroom. Re secure cs16 strap in closet at entry. 10/72024 Per previous notes. Leak at 3" ABS line. 10/8/2024 10/10/24:per previous notes leak at first floor bathtub. Pour back required underneath bathtub. |
|
10/15/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 10/15/24 corrections made |