| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/28/2024 | RSBU - Building Final | Re-inspection required | 10/28/24: Hand rails at stairs missing, all exterior piping must be coated for UV protection, first floor lighting no power at multiple circuits, clearance around HVAC Condenser required 3". Caps at drive way clean out required, attic access required. Dishwasher not installed. receptacle spacing at 2nd story bedrooms greater than 12’. | |
| 10/30/2024 | RSBU - Building Final | Re-inspection required | 10-30-24, receptacle spacing at 2nd story bedrooms greater than 12' | |
| 10/31/2024 | RSBU - Building Final | Passed | greater than 12' 10-31-24, building final approved. |