Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Roof NailingĀ
| Date |
Description |
Inspector |
Results |
Comments |
| 06/09/2025 |
COT - RSBU - Roof NailingĀ |
|
Re-inspection required |
6-9-25: add nails to exterior sheathing and at interior shear walls at marked locations, add shot pins to marked location and nail those marked in red flush to sill plate, add H-25's 3-pt bearing girder truss at garage/ bedroom 2, beam to post connections require 10 nails above/below interconnecting points-see Detail S5.1-6., loose roof panel at master suite bathroom. |
| 06/10/2025 |
COT - RSBU - Roof NailingĀ |
|
Passed |
6-10-25: roof nailing approved. |