Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
Permit Number - TC-MDP-0123-00206
Inspection Description - COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
Inspection Status - Re-inspection required
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/18/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Re-inspection required | Seal penetrations going from first floor to second floor by kitchen island, seal top plate penetrations at next gen. Kitchen hood, refrigerator must run on its own circuit per E1 plans, dwv not under test, correctly install fireblocking at duct chase, fire block all duct chases, bathtub not under test, Fireblock all ceiling to floor penetrations, add stud shoe to middle over notched stud in double sink bathroom. | |
04/19/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Canceled | Cancelled per Craig. | |
04/24/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Re-inspection required | Refrigerator must run on its own circuit per E1 plans, dwv not under test at second floor, shower not under test, add stud shoe to middle over notched stud in double sink bathroom, missing clean outs, plumbing not per plans. Make proper corrections according to plans or revise plans showing current layout of electric and plumbing work done and provide updated city stamped plans at Final. | |
04/25/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Canceled | Cancelled per Craig. | |
04/26/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed |