Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCPL - Rough Soil
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/19/2026 | COT - LCPL - Rough Soil | Partial Pass | 5/19/2016 UG plumbing in basement at east and north walls approved. Okay to backfill progress areas. Shading required. | |
| 06/02/2026 | COT - LCPL - Rough Soil | Partial Pass | Underground plumbing approved at all general areas. Pending 18 E Ochoa (barbershop) north east corner. Okay to backfill all progress areas. Shading required. | |
| 06/10/2026 | COT - LCPL - Rough Soil | Partial Pass | 6-10-26: underground plumbing at barber shop & at basement bar verified under test. Add plastic bushings to protect DWV at bar pony wall. Also, verified 3-3" Schedule 80 electrical conduits for upstairs future use & 2-2 1/2" and 2-3" conduits stemming into barber shop area from north exterior wall of barber shop. Okay to backfill progress areas using shading materials. | |
| 06/18/2026 | COT - LCPL - Rough Soil | Partial Pass | 6.18.26 Needed electrical underground, but was not on the permit. |