Inspection Status: Re-inspection required

Inspection History: COT - LCBU - Framing

Date Description Inspector Results Comments
COT - LCBU - Framing Re-inspection required 4-7-26: plans call for 2x plates at bedroom 6 and anchor bolts at 4' for exterior walls. Plans also call for 2x6 studs t 16" o.c. Together with 2x6 sill plates. Have architect submit a revision clarifying whether 2x4 's are allowed and at 24" o.c.. Shot pins are required within 6" at the ends of each plate and spaced 32"o.c. thereafter. 10-16d nails are required at a to[ plate splice. Stopped inspection-additional items may be noted.
04/10/2026 COT - LCBU - Framing Re-inspection required (with fee) 4-10-26: missing shot pins throughout-shot pins are required within 6" at the ends of each plate. Add shot pins at marked locations, seal all penetrations at top plates, add nails A35's., frame out cassettes, wrap DWV at shower-provide pictures prior to pour back and add shot pins to sill plates at shower.
04/15/2026 COT - LCBU - Framing Partial Pass 4-15-26: framing approved. Okay to install drywall but call for a drywall screw inspection prior to tape & texture. Add screws 3/8" from joints and do not over penetrate screws more than 1/32".
04/29/2026 COT - LCBU - Framing Passed 4/29/2026
Gypsum 5/8" type-x nail schedule verified at garage conversion to bedrooms. Okay to cover.