Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Inspection Status: Partial Pass

Inspection History: COT - LCBU - Framing

Date Description Inspector Results Comments
04/09/2026 COT - LCBU - Framing Partial Pass 4-9-26: add shot pins within 6" (minimum of 2) at the ends of the pony wall sill plate. Will check for correction at intermediates.
05/15/2026 COT - LCBU - Framing Partial Pass 5-15-26: framing approved. Please schedule a drywall screw inspection prior to tape & texture. Install screws 7" o.c. throughout at firewalls.
06/09/2026 COT - LCBU - Framing Passed 6-9-26: okay to tape & texture drywall.