Inspection Status: Partial Pass
Inspection History: COT - LCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 04/09/2026 |
COT - LCBU - Framing |
|
Partial Pass |
4-9-26: add shot pins within 6" (minimum of 2) at the ends of the pony wall sill plate. Will check for correction at intermediates. |
| 05/15/2026 |
COT - LCBU - Framing |
|
Partial Pass |
5-15-26: framing approved. Please schedule a drywall screw inspection prior to tape & texture. Install screws 7" o.c. throughout at firewalls. |
| 06/09/2026 |
COT - LCBU - Framing |
|
Passed |
6-9-26: okay to tape & texture drywall. |