Inspection Status: Partial Pass
Inspection History: COT - LCBU - Building Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 09/05/2025 |
COT - LCBU - Building Progress |
|
Partial Pass |
|
| 09/24/2025 |
COT - LCBU - Building Progress |
|
Partial Pass |
9/24/25: framing approved ok to onside courtyard area/bar area |
| 09/25/2025 |
COT - LCBU - Building Progress |
|
Partial Pass |
9/25/2025 in wall electrical approved. courtyard area/bar area. Okay to proceed progress areas. |
| 09/29/2025 |
COT - LCBU - Building Progress |
|
Partial Pass |
9-27-25: in wall domestic & DWV plumbing intermediate at court yard bar approved-okay to continue with construction at progress areas. |
| 10/01/2025 |
COT - LCBU - Building Progress |
|
Partial Pass |
|
| 10/06/2025 |
COT - LCBU - Building Progress |
|
Passed |
|